Hidroelectrica has completed the modernization of hydro unit 1 within the Slatina HPP
Hidroelectrica signed the documents for the commissioning of hydro unit 1 (HA1) within the Slatina Hydroelectric Power Plant, an important objective in the company’s portfolio.
The modernization works were completed by Hidroserv S.A., Hidroelectrica’s total investment amounting to over 26 million RON.
The main purpose of the work was to prepare HA 1 equipment and facilities for a new operating cycle of at least 30 years.
“The modernization of Hydro unit 1 within HPP Slatina marks the completion of a new stage in our mission to ensure a sustainable source of electricity for Romania. We are proud to have succeeded in restoring the efficient operation of this hydro unit, turning it into a vital asset for the national energy system. The investment we are finalizing today confirms Hidroelectrica’s solid commitment to the development and modernization of the energy infrastructure, so that we can continue to provide green and safe electricity for all citizens” – said Bogdan Badea, president of the Hidroelectrica directorate.
During the modernization process, the contract – initially awarded to Romelectro , was terminated due to delays in February 2022, and later resumed – successfully, by Hidroserv S.A.
Hidroelectrica is the largest producer of green energy in Romania and the main provider of technological services needed in the National Energy System, being a vital company for a strategic sector, with implications for national security. The company operates a number of 187 power plants, with a hydropower capacity of 6.3 GW. Added to them is the Crucea wind farm, with an installed power of 108 MW.